§ A168-18. Curbs.  


Latest version.
  • Where installed, concrete curbs shall be constructed on both sides of the street as shown in Figure 1C prior to laying street pavement to the dimensions and specifications shown in Figure 4. A base course of six inches of subbase material, tamped and free of stone over two inches in thickness, shall be laid under all curbing. An air-entrained concrete mix of 4,000 pounds per square inch after 28 days shall be used and shall be finished and cured to the satisfaction of the Town Commissioner of Public Works and Town Engineer. The developer, at his own expense, shall replace any curbing that has settled, cracked, scaled or has become damaged in any way by the developer before and within the one-year maintenance period after dedication. Curbs shall be depressed four inches at all driveways. Stone curbs or precast curbs may be substituted on approval of the Town Commissioner of Public Works and Town Engineer.
Amended 6-23-1988 by L.L. No. 1-1988; 3-24-2005 by L.L. No. 1-2005